Further, the conversion to combined cycle of the the Santa Barbara (400MW) plant will be brought forward and completed in 24 months
Rome, July 2, 2003
The Board of Directors of Enel, given the situation of Italys electricity sector, examined and approved the initiatives proposed by Chief Executive Paolo Scaroni aimed at creating reserve capacity to be activated in emergencies (about 100 hours per year). The plan will be valid from both the operational and economic points of view.The initiative consists of:
- The re-activation of a number of idled plants, with a total capacity of 1,200MW, within the next 12 months and for an investment of about 25 million euro.
-
- The bringing forward of the conversion to combined cycled natural gas of the Santa Barbara plant. The conversion, with a capacity of about 400MW, will be completed in 24 months with a total investment of 170 million euro.
The plants being re-activated are:
Plant Province Capacity (MW)
Reactivation
time (months)
Campomarino Campobasso 88 3
Maddaloni Caserta 88 5
Carpi Modena 176 5
Camerata Picena Ancona 104 7
Larino Campobasso 246 9-11
Giugliano Napoli 176 12
Montalto Viterbo 240 12
Alessandria Alessandria 88 12
1206